STADIUM

Emirates Stadium

   This section contains a large amount of information about the construction of Emirates Stadium.It contains many facts and statistics on the new field.Choose one of the options on the right side by a series of different aspects, including

Schedule

Emirates Stadium was opened in July 2006, just over three years after demolition began on the site. Go to the full plan as Arsenal's new home took shape.
March 15, 2006 - May 1 2006, Pitch construction completedDiamond Club just completedMat Level 1, Level 2 bars and a restaurant completeSeat began installation
January 15, 2006 - 15 March
2006 began lining Podium
bulkfill Pitch and DrainageCarpet and hostels joineryStart megastore and decorating services
November 15 - 23 December
2005 the club will Bars
Emirates Stadium in red, "began at the base of the NortheastThe speakers are - as well as a rooftop terrace in the WestCompletion of the sloping facade (glass on the outside)Completion of the direction of the glass boxValas ads beganGas meter installedWater reservoir and operationInstallation of catering equipment (concession and kitchen), hefinished floor VIP passes started
 
October 7 - November 15, 
2005 bracketing Seating
Complete an application abroadPower
September 10, 2005,North stand precast concrete terraces lower level completemain roof lining - Accessories North, East and West is progressing wellExterior windows - almost completeInstalling turnstiles beganNorth Stand began commissioning (testing of mechanical and electrical)Office Building steel structure complete
August 09, 2005,South resign / Club precast concrete patios fullNorth Stand service liftsS1 and ceilings began to level 0Sto-rendered competition was initiated at 0 (textured finish applied to the block wall work)Final electrical panels suppliedHQ steel construction started
July - July 2005 AoûtGenerators installed in North and South StandsWest Stand and the use ofSouth Stand escalator installedCore Mesh bracketry began (in brackets in the fixed core and knitted ready to receive external)South Stand began installation of a liftHQ concrete infrastructure complete
June - July, 2005,Main fired roofThe main roof installation beganEasily installed and South Substations
May 10, 2005West, north and east to central / precast concrete terrace club level, in fullExecutive Level 2 glasses full fieldLevel 1 glass bowl startedRatchet began metal bracketHQ incomplete base (offices Arsenal)
April 9, 2005,South Stand-top box / precast concrete terraces and concludedSouth bound to the main roof in place untilWest, Northeast and installation of escalatorsInternal plasterboarding startedWest and north of the substation units shippedsiding and windows started back button
5 March 2005South Stand completed metal roof terraceInstallation began to liftplantroom cooler at 4 poundsNorthern and western slope / club level terrace level precast concrete began
5 February 2005,South stand on board began to level 3Core A1 main walls are filledflattening (smooth floor) began S1, Level 2Level 0 Bathrooms General Admission started Wallpapers
January 2005,South board began to stand levelNorth Stand Level Club Level Rakes rays beganMechanical and electrical started to rise north
April 12,2004-January 7,2005,Core B1 level of the four main walls filledNorth main trusses lifted into positionwire mesh roof of the South began to mountMechanical and electrical started west (vertical wells for mechanical and electrical services)
6 December 2004,South accumulate completedSouth Stand Level 0 board beganNorthern and Upper East / classification box precast concrete layer completeFacades started
2 November 2004,Existing waste and recycling center Demolition completedSouth began to accumulateCore A1 Concrete work beganSouth Stand Foundation startedUpper West stand / box precast concrete deck with a completeWest Stand Level 4 of the roof started
August 14 to October 1, 2004Box and high-level precast concrete terraces beganEast and North are in full board-level 3 0East Stand Block beganWest Stand mechanical and electrical installations startedmetal truss roof startedLevel 2 devices made of glass began Box
July to August 2004,Core concrete work began B1West Stand Level 0 Level 3 full boardWest Stand Upper Terrace steel beganBlock West Stand beganSouth Bridge started on the railwaysWaste Recycling Centre and came to the conclusion, the practiceAnd demolition waste recycling center began
5 June 2004,
B2 and C2 Cores walls of the main conclusion of the fourth level
West Stand Class 0-Tier 2 full slabs (concrete floor)North Stand Level 0 plate fullWaste and Recycling Centre began to emerge as a compactorMetal Assembly of the South Bridge is completed
6 May 2004,Core D1 concrete work has startedEast Stand began construction of the countryNorth Stand Foundation startedNorth Bridge lifted into position on the rail
3 April 
2004 Cores A2 and D2-completed main wall of Level 4
Western, Eastern and Northern piling completedEast Stand Foundation startedCore C1 concrete work startedInstallation of metal bridge began SouthNorth Bridge full of metal parts
2 March 2004,Cores B2 and C2 concrete work beganWest is the country's construction beganInput power voltage and waste recycling center
1 March 2004 complete demolition phaseCells in the west and eastColors A2 and D2 in the course of constructionWest Stand Foundation startedNorthern Assembly began the metal bridgeStressesTotal project cost is 390 million dollars.1800 new jobs will be created in the borough of Islington as a result of the new stadium project.More than 2,000 new homes will be built in Islington, in the project.   On top of this project will be 1,000 construction workers working on a new stadium.The location of the new stadium is 17 hectares.The new stadium will have a capacity of 60,000 spectators.Height of the new stadium will be 41.9 m from ground level to the roof.   Two important points in mind the club team of the project were good enough to be as good as Highbury and create a stimulating atmosphere in the stadium over design.1140000 is the number of fans expected to pursue a new stadium in the league in a season (average at Highbury - 722,795).There will be 150 boxes in the new stadium, compared with 48 boxes at Highbury.The new stadium will have a total capacity of the executive boxes to serve up to 2,000 meals a day.There will be about 250 points catering services around the new stadium.   More than 900 toilets will be in the new stadium, with 370 meters of urinals and toilets for people with disabilities 113thMore than 2,500 legal documents have been signed for the project to complete disappearance.There will be 41 places of television cameras at the stadium, and 215 seats for the media.The stadium will host a new 1.000 m2 hypermarket merchandising.Arsenal has appointed Sir Robert McAlpine Ltd. works on the project in January 2002.   Past projects that Sir Robert McAlpine was responsible of a new stadium at Hampden Park in Glasgow, Centenary Stand at West Ham United, the Millennium Dome and the Bullring in Birmingham.The new stadium was designed by HOK Sport architects Stadium in Sydney, Australia, the English National Stadium Wembley, the Royal Ascot race track and Wimbledon Centre Court.More than 25,000 cubic yards of contamination have been removed from all sites, so that for this project.There will be up to 250 wheelchair users at the new stadium. These positions will be provided at all levels of public and private sectors around the building.Size of grass will be 113 m by 76 m. In comparison with 105 m 70 m in Highbury.   More than 60,000 m3 of concrete will be used in a structure which is enough to fill the bath at Highbury team of more than 7500 times, enough to fill the height of three storeys.10,000 tons of reinforcing steel will be used at the stadium, which is the equivalent weight of more than 300 coaches of the team.   3000 tons of steel tubular roof will be the main (there are 100 000 tonnes in the current North Bank).There will be 33,000 m of concrete terraces.The new stadium of 15.000 m2 of glazed area equivalent of two football pitches.   There will be 4.500 m metal railings.Sports complex will include a door 2000.There will be 100 storeys, which is enough for all at the top of Canary Wharf twice.There will be 13 elevators and escalators 5th Four levels of seating are covered roof of approximately 30,000 m2 (football field covers an area about 8.600 m2).To improve the quality of potential in the new stadium, run computer simulations to study the sun's light and ventilation on the spot.

FAQ
What is the value of the cost of the stadium project?

   The total cost of the project as a whole is 390 million dollars. This includes the construction of Emirates Stadium, the new unit to recycle waste, and relocation of local firms and legal services.

What is the capacity of Emirates Stadium?

60,000

How was the venue for the stadium?

   The aim of the club has always been to stay close to our current home at Highbury.The site chosen to ensure that Arsenal remains the Islington neighborhood of the club's home since 1913.

Why not extend Highbury?

   Arsenal Stadium is located in a residential district with a high density, thus limiting the possibility of increasing capacity.

In the long term, the Emirates Stadium, used for another event?

   The club has planning permission for a limited number of other football events should not be held at the Emirates Stadium. However, in the first place, the stadium is the home of Arsenal Football Club and the Club has no definite plans with regard to the events of football in no time.


How do you finance the project? 

   To finance this highly complex project, Ashburton Properties, a subsidiary of Arsenal Holdings plc was founded and received a loan of U.S. $ 260million senior stadium facilities banking group. This group includes banks: Royal Bank of Scotland PLC, Espirito Santo Investment, Bank of Ireland, Allied Irish Banks PLC, CIT Group Structured Finance (UK) Limited and HSH Nordbank AG.Interest on the principal debt is a commercial rate established for more than 14 years.   Arsenal will cover the remaining cost of the stadium project with funds from Granada, Nike and the sale of surplus land assets for the stadium site. Moreover, since the club moved in 2006, Arsenal have planning permission for residential development of Highbury. The club is actively seeking to refinance a loan than $ 260million at the beginning of 2006. Director Keith Edelman said:"We believe that the greatest danger is behind us, because most of the major technical challenges were met and the physical structure is there. 14 years (the duration of the outstanding loan) is a short period for the asset, which we hope 50, 75 and more years. That is why we try to go 25 years with a lower interest rate. If we can do to reduce our debt payments on an annual basis and allows us to have more free money. "

What happens to Highbury?

   Arsenal Stadium, Highbury was converted into 711 apartments, facilities such as fitness center, health center, day care and business unit. Pavilion East and West facades and marble halls, and other key elements of phase to the Art Deco sunburst panels of glazing to be retained and incorporated into the new system, called "Stadium - Highbury Square.   It is a Grade II listed Highbury stands, and against the West Stand will be transformed into a high-spec apartments, many with views of the field that has seen so many beautiful moments of football in 93 years. Posts will be removed and the ground becomes a garden of about two hectares. North and South Stands will be replaced by new residential buildings designed to blend with the East and West stands.   Luxury resort continues pool and fitness center in the basement in height. There will also be 24 hours concierge service and parking for cars and bicycles. Perhaps best of all, walk to the stadium will be the new home of Arsenal, Emirates Stadium, where most of the world will be played from August 2006.To learn more www.thestadium highbury.com or call marketing suite on T: 0845 2626000 or joint selling agents: Savills on T: 020 7472 5000 or visit www.savills.com, Anthony Green & Spencer on T: 020 7609 1111 or visit www.anthonygreenandspencer.com

What happens to land at Highbury and the public will have access to?

   Lawn will be transformed into a garden will be open to members of the local community, according to company management, which will set the stage, when development is completed. A memorial garden will be part of garden and will also be open to the public.

What happens to the artifacts from Highbury? It will be an auction?

   Content Highbury will be auctioned off dramatically just before the change of the club at the Emirates Stadium next summer. The auction will take place over three days at Highbury in the summer of next year, the North Bank Stand is designed to thousands of potential buyers in the case.Arsenal fans and collectors of memorabilia from the football world will be able to buy goods is measured from the famous old stadium, or attending the auction in person or connect to a live event.   Since the East Stand is a cultural monument and is situated on the west holds the Art Deco style in 1930, some elements remain at Highbury and some recreated in the Emirates Stadium. Although the specific auction lot was not confirmed, it is certain that it contains thousands of objects truly historic stadium. The club expects that demand will be enormous and we ask those interested to attend the event and auction activities throughout the year visitwww.highburyauction.com and register their details.

There will be a museum at the Emirates Stadium?

   Yes, plans are hard on a new museum that will take 12 years to attract the North Bank at Highbury. Memories and it is now on display at the Emirates Stadium would be exceeded. While exact plans are still under investigation, the original proposals offer a very modern design that is sure to engage and excite the fans.

The event will take place, or the closing ceremony to say goodbye to Highbury?

A number of plans is expected to submit final farewell to Highbury, including activities since the last game against Wigan. Confirmation of all activities will be included in the new year.

What is the countdown?

   Countdown is a reminder of how long the club was officially left before closing the turnstiles of its football games at Highbury. So the countdown for the last match against Wigan at the end of the closing ceremony, which took place after the match.The event will close at 6 pm 30 May 7, 2006.

How do I get tickets for matches at the Emirates Stadium?

   Fans can secure their position on the ticket waiting lists, joining Arsenal, a club membership.Arsenal offers new and existing club members with the greatest supporters. " Benefits of membership include special package Highbury Farewell membership, which includes exclusive DVD of scenes and a "collection of Highbury - hardcover book with stunning images of 100 captivating Highbury from 1913 to the present, as well as a good book, which offers various discounts on local and club sponsor. Members also have the opportunity to participate in exclusive events and their use of the website through which tickets can be purchased exclusive. Fans can refer to www.arsenal.com / membership or call the customer subscription services online Help 343 0870 0870th   Due to high demand, it may be unlikely that many fans in the season ticket waiting list will be able to get ticket at the Emirates Stadium. Proponents of this position are invited to consider the club-level seats.   Club Level, which forms a layer around the Emirates Stadium in Cash Management, will provide fans a warm welcome, and some of the best lines of sight of land. This region will have its own dedicated inputs and will be given an enviable number of world-class bars, restaurants and lounges, providing fans the entire game day experience.   It is essential that all the fans who have yet to book their place in the club should visitwww.arsenal.com / clublevel or call to register at club level on 0845 262 0001 as soon as possible to avoid disappointment.

Affordable housing should be provided for the development of Arsenal Stadium is concentrated in one area or spread across the developing world?

   There will be an affordable housing project along the southern boundary adjacent to Aubert Court. In addition, there will be affordable housing scattered in other parts of the developing world, including inside the stalls and renovated along Highbury Hill.

There is affordable housing and other developments relating to the relocation of the stadium?

   Arsenal helped create affordable housing through a number of developments associated with the stadium project. 40% of all housing units will be available.Just under 400 homes are for sale through a shared interest in the majority of sites being developed by the Development Programme for Arsenal. Newlon Housing Trust has properties available:
Eden Grove - 1, 2 and 3 / 4Estimated date of occupancy - March 2006
Triangle North - 1, 2 and 3 / 4Estimated occupancy date - July 2006
Caledonian Road - one bedroom apartments and 2Estimated date of occupancy - October 2006 - 2007 April
Hornsey Street - 1 and 2 / 4Estimated occupancy date - November 2006
Highbury Square - 1 and 2 / 4Estimated date of occupancy - September 2007
Queensland Road - 1 and 2 / 4Estimated date of occupancy - March 2008(To be eligible for shared ownership to any of these developments, must be living or working in Islington keyworker or work in London.)

How to cope with public transport additional 22,000 spectators?

   Public transport in Arsenal is already the best in the Premier League in a vote that 70% of supporters travel by other modes of passenger vehicles.TfL, Arsenal and Islington Council are in the final stages of development of transport plans to promote the Emirates Stadium when it opened in August 2006, which will host more traveling to promote and ensure safe and reliable local and two underground metro lines (Piccadilly and Victoria), national rail and many bus services that provide access to the site.   The first details of the transport plan will be announced later this season, so everyone will know who will be traveling system in place even before opening the new stadium and fans, which allows you to start planning trips to new and the room.Measures to improve transport infrastructure around the Emirates Stadium is in full swing. And improvements in the vicinity of subway stations and guidelines will be a comprehensive approach to environmental management of network traffic, fine tuning and improvement of pedestrian facilities for parking bicycles.   The club will provide information on all the new stadiums and ticket offers, which actively encourage supporters to avoid traveling in our new stadium by car. This should lead to a high percentage of people who travel to the Emirates Stadium by public transport.   The club is very confident that the travel plans will allow our fans will be able to access and leave the Emirates Stadium in a safe manner and do not have a serious impact on the local community.

There will be parking at the new stadium?

   There is limited parking for disabled supporters. Emirates Stadium is located in an area that will have a huge event day parking scheme in operation. Only car owners with a residence permit may park on the street in designated areas.